[FIX] mrp: Changing the routing on a bom
When changing the routing on a bom, "Consumed in Operation" indicated
in some lines of the BoM did not correspond to the routing used.
So the system did not link it to a workorder and it was never consumed when
a MO was processed.
Now the "Consumed in operation" are reset when the routing is changed.
opw:807560